Client: Evara

Main Contractor:  B&C Contractors

Architect: Conroy Crowe Kelly Architects (CCK)

Engineer: T3 & T4 Barrett Mahony Consulting Engineers

T5 Waterman, Moylan Engineering Consultants

Cherrywood T3, T4 and T5 is a significant residential development in Dublin comprising apartment buildings and duplex homes designed to provide high-quality modern living spaces. Arc Engineering was appointed by B&C Contractors to design, manufacture and install a complex package of cantilevered balconies across the development.

The project consisted of 59 offsite manufactured balconies in total, including 52 balconies to the T5 apartment and duplex blocks and a further 7 balconies to the T3 duplex development. The works incorporated Schöck cast-in thermal anchors, hot-dip galvanised steel support stubs, galvanised steel balcony structures, aluminium decking systems, vertical bar balustrades with integrated glass windbreaks and bespoke powder-coated aluminium soffits incorporating concealed rainwater management.

While the apartment balconies were challenging in their own right, the duplex balconies presented the most significant engineering and coordination challenges. Unlike typical cantilevered balconies, which are generally around 1.6 metres deep, the Cherrywood duplex balconies were required to provide approximately 10m² of usable external space. This increased the balcony depth to approximately 2.6 metres, substantially increasing loading, structural demands and interface requirements.

  • 59 offsite manufactured cantilevered balconies
  • Galvanised mild steel balcony bases
  • Vertical bar balustrades with integrated glass windbreaks
  • Powder coated aluminium soffits incorporating concealed rainwater management